On this page I report a list as complete as possible of the terms used in project management in English and Italian.
When available, there is a link to a page that delves into the item.
Not all project management terms in English have an equally intuitive correspondence in Italian. For example, the term Deliverable, which is essential in English, struggles to find a correspondence with an equally immediate meaning in Italian. Any suggestions are welcome in the comments.
On the other hand, there are English terms that seem similar to Italian, but they are false friends, for example "scope" in English, which translates as "scope" in Italian and defines what is inside and what is outside the project scope.
Acceptance criteria> Acceptance criteria (used in the UAT or User Acceptance Test)
Activity> Activities
Actual cost (AC)> Actual cost
Actual duration> Effective duration
Actual finish date> Actual finish date
Actual start date> Actual start date
Analogous estimating> Estimating by analogy
Assumptions> Assumptions / Assumptions. They are facts or conditions that are believed to be true at the time the project is defined. However, there is no certainty that these assumptions are true for the entire duration of the project, so it is customary to associate a risk with each assumption.
Bar chart> Bar chart
Baseline> Baseline
Bottom-up estimating> Bottom-up estimating
Brainstorming> Brainstorming
Budget> Budget
Budget at completion (BAC)> Budget at completion
Buffer> Buffer
Change control> Change control
Change control board (CCB)> Change management committee
Change request> Change request
Checklist> Checklist
Communication management plan> Communication management plan
Compensation> Consideration
Configuration management system
Constraint> Constraint
Contingency> Contingency
Contingency allowance> Provision for contingency
Contract management plan> Contract management plan
Contract statement of work> Contract specifications
Control account (CA)> Control point
Control account plan (CAP)> Control point plan
Control chart> Control chart
Corrective action> Corrective action
Cost control> Cost control center
Cost estimating> Cost estimating
Cost plus fee (CPF) contract> Expense reimbursement contract plus variable fee
Cost plus fixed fee (CPFF) contract> Expense reimbursement contract plus fixed fee
Cost plus incentive fee (CPIF) contract> Expense reimbursement contract plus incentive
Cost variance (CV)> Cost variance
Crashing> Time / Activity Compression
Critical activity> Activity that is on the critical path
Critical chain method> Critical path method
Critical path> Critical path
Defect repair> Correction of a defect
Deliverable> Deliverable, Delivery, product, under-product, output, result
Delphi technique> Delphi technique
Dependency> Dependence
Duration> Duration
Early finish date> Minimum end date
Early start date> Minimum start date
Earned value (EV)> Generated value
Earned value management (EVM)
Earned value technique (EVT)
Effort> Commitment
Enterprise environmental factors> Environmental factors relevant to the company
Estimate> Estimate
Estimate at completion (EAC)> Estimate at completion
Estimate to complete (ETC)> Estimate of the work to be completed
Expected monetary value (EMV) analysis> Analysis of the expected monetary value
Expert judgment> Expert opinion
Fast tracking> Speed up activities
Finish date> End date
Finish to finish> Dependency relationship in which the end of one activity constrains the end of the other
Finish to start> Dependency relationship in which the end of one activity constrains the start of the other
Firm fixed-price (FFP) contract> Fixed-price contract (package)
Fixed price or lump-sum contract> Fixed price or lump sum contract
Fixed-price contract
Float> Slip margin possible without impact on the project
Free float> Time slippage margin of an activity with no impact on the next activity.
Gantt chart> Gantt chart
Ground rules> Ground rules (e.g. how to behave in meetings)
Historical information> Historical information
Inspection> Inspection (in the context of Quality Control)
Integrated change control> Integrated change control
Invitation for bid (IFB)> Call for tenders
Issue> Issue (can be questions, observations, requests, problems, criticalities)
Knowledge> Knowledge
Lag> Lag (Time between the start of two activities linked by a relationship)
Late finish date> Maximum end date
Late start date> Maximum start date
Lead> Lead (Lead time of an activity in a finish to start relationship)
Lessons learned> Teachings
Level of effort (LOE)> Level of effort
Leveling> Leveling
Life cycle> Life cycle
Log> Log
Manage stakeholders> Manage stakeholders
Milestone> Milestone (Main activity or event)
Monitoring> Monitoring
Monitoring and controlling project work> Monitor and control project work
Near-critical activity> Activity close to being on the critical path
Objective> Objective
Off-specification> Specification required but not tracked (Deepening)
Organization chart> Organization chart
Organizational breakdown structure (OBS)> Organizational diagram with breakdown of work packages by department or function
Original duration> Initially estimated duration
Output> Result
Parametric estimating> Parametric estimation (based on analogies or parameters)
Path convergence> Path convergence (point of ...)
Path divergence> Path divergence (Point of ...)
Percent complete> Percent complete
Perform quality assurance> Carry out quality assurance processes
Perform quality control> Perform quality controls
Performance measurement baseline> Baseline (starting point or base) for performance measurement
Performance reporting> Performance reporting
Performance reports> Performance report
Performing organization> Organization that manages the project
Phase> Project phase
Planned finish date> Planned finish date
Planned start date> Planned start date
Planned value (PV)> Planned value
Planning processes> Planning processes
Plan procurement> Plan supplies
Planning wave> Planning for progressive processing
Portfolio> Portfolio (of projects)
Portfolio management> Portfolio management
Precedence diagramming method (PDM)> Method used to create a networked project calendar in the CPM (Critical Path Method)
Precedence relationship> Precedence relationship
Predecessor activity> Predecessor activity
Preventive action> Preventive action (to avoid a deviation)
Probability and impact matrix> Probability and impact matrix (In risk management)
Procedures> Procedure
Process> Process
Process group> Process group
Procurement documents> Procurement documents
Procurement management plan> Procurement management plan
Product life cycle> Product life cycle
Product scope> Product scope (deepening)
Program> Program
Program management> Program management
Progressive elaboration> Progressive processing
Project> Project
Project charter> Project charter
Project communications management> Project communication management
Project initiation> Starting the project
Project integration management> Project integration management
Project life cycle> Project life cycle
Project management> Project management
Project management body of knowledge (PMBOK)> Project management body of knowledge (PMBOK)
Project management information system (PMIS)> Project management information system (PMIS)
Project management office (PMO)> Project management office (PMO)
Project management plan> Project management plan
Project management process> Project management process
Project management process group> Project management process group
Project management professional (PMP)> Project management professional (PMP)
Project management software> Project management software
Project management system> Project management system
Project management team> Project management team
Project manager> Project manager (blog post)
Project organization chart> Project organization chart
Project phase> Project phase
Project process groups> Project process groups
Project procurement management> Project procurement management
Project quality management> Project quality management
Project risk management> Project risk management
Project schedule> Project calendar
Project scope> Project scope (Deepening)
Project scope management> Project scope management
Project scope statement> Description of the project scope
Project sponsor> Project sponsor
Project stakeholder> Stakeholder (stakeholder) of the project
Project team> Project team
Qualitative risk analysis> Qualitative risk analysis
Quality management plan> Project quality management plan
Quality planning> Quality planning (Quality must be planned, as well as measured)
Quantitative risk analysis> Quantitative risk analysis
Remaining duration> Residual duration
Request for information> Request for information (used in procurement)
Request for proposal (RFP)> Request for proposal / offer
Request for quotation (RFQ)> Request for quotation
Requirement> Requirement
Reserve> Reserve
Residual risk> Residual risk (after risk management itself)
Resource> Resource / Resources
Resource breakdown structure (RBS)> Resource breakdown
Responsibility assignment matrix (RAM)> Responsibility assignment matrix
Rework> Rework
Reserve analysis> Reserve analysis
Risk> Risk
Risk acceptance> Risk acceptance
Risk log - risk register> Risk register
Risk identification> Risk identification
Risk management plan> Risk management plan
Risk mitigation> Risk mitigation
Risk transference> Transfer of risk (e.g. buying insurance)
Role> Role
Rolling wave planning > Progressive scheduling - Floating window scheduling
Root cause analysis> Root cause analysis
Schedule> Calendar
Schedule compression> Calendar compression
Scope> Scope (Deepening)
Scope baseline> Scope baseline
Scope change> Change the scope
Scope control> Scope control
Scope creep> Uncontrolled change of scope, phenomenon through which activities are added to the project that should not be carried out
Scope verification> Scope verification
Secondary risk> Derivative (collateral) risk
Slack> Margin of tolerance
Specification> Specification
Specification limits> Specification limits
Start to finish> Start-to-finish dependence
Start to start> Start-to-start dependency
Statement of work (SOW)> Specifications
Subproject> Subproject
Successor> Successor activity
Task> Task or activity
Template> Document scheme
Three point estimate> Three point estimate (high medium low)
Time and material (T&M) contract> time and material contract (refund)
Total float> Total float
Total quality management (TQM)> Total quality management
Tracking> Monitoring (Deepening 1) (Deepening 2)
Trend analysis> Trend analysis
Verification> Verification
Virtual team> Remote workgroup connectedor through technologies
War room> Project control room (war room)
WBS dictionary> Work Break Down Structure Dictionary
Work> work
Work authorizarion> Work authorization
Work breakdown structure WBS>
Work package> Work package
Workaround> Temporary Solition
A lead allows an acceleration of the successor activity. For example, on a project to construct a new office building, the landscaping could be scheduled to start 2 weeks prior to the scheduled punch list completion. This would be shown as a finish-to-start with a 2-week lead.
A lag directs a delay in the successor activity. For example, a technical writing team can begin editing the draft of a large document 15 days after they begin writing it. This could be shown as a start-to-start relationship with a 15-day lag.